Today SPS (Specialty Pumping Services) moved their equipment onto the Llama 13-1 location, rigged up, and began pumping in 4000 gals of 20% HCL Acid with approx 650 bbls of sw flush. The acid job was done in four stages. 1000 gals of acid followed by approx 150 bbls of sw. Repeat the process four times, rig down, move off location.  Acid Frac complete.

The entire job went as could be expected. After completing the job the well pressure dropped to zero and actually went on vacuum which suggests that the acid was pumped deep out into the formation.

Tomorrow, D & M Well Service will run in the hole with the rods, tubing & down hole pump. Adam’s Tank will build the pad for the Pumpjack which will be delivered and set up Thursday morning.

A few pic’s below of today’s activities.  

Stay tuned…..more tomorrow.