Llama Update 6.25

June 25 2020

Yesterday, East Central Electric did get the Transformers and Meter bases installed on the poles next to the 13-1 & 13-2 locations, later today they returned to hang the meters (see Pic’s).

Adam’s tank completed the installation of the tank battery as well as the flowlines and connections.

Emerald Oil Co completed the laying of all the remaining electric line, made all the connections, and have the entire system ready to turn on tomorrow on the 13-1 well.

Tomorrow they will complete the hooking up of the electric lines to the panel box, phase converter, and motor on the 13-2 well (it was still too muddy to get to the location today). Tomorrow both wells should be ready to turn on by noon.