Llama Update 7.2

This morning Adam’s Tank & Lease Service was able to get the weights balanced on the Llama 13-2 and get it turned back on, we probably lost about 14 hours pumping time. We are still getting gas up the back side and a good oil cut. Both should start improving soon.

The Llama 13-1 well has continued to pump mostly acid flush with some gas building on the back side.  

We did realize a slight miscalculation. In addition to the 760 BBls of Flush that we pumped into the well during the Acid job, we also loaded the hole to the top in order to create a pressure cap while we had it shut-in prior to turning on the pumpjack. This consists of approx 60 BBls of SW, not a big deal but just a few more BBls we need to get back before we get to the good stuff.