Blog

Llama Update 6.19

Today was fairly event free. East Central Electric was scheduled to hang the transformer and meter at the Llama 13-2 location,….they were a no show. They have also been scheduled to hang the transformer and meter at the Llama 13-1 location tomorrow morning.  We will see what happens, possibly they will do both tomorrow. Adam’s […]

Llama Update 6.16

Since our last update we have been able to get all the Oil & SW flowlines laid, trenched, and buried on the 13-2 well. We only have the Reta cable for electricity to lay, still waiting on East Central Electricity to hang a transformer and meter. Today, on the 13-1 well we were able to […]

Llama Update 6.9

Today SPS (Specialty Pumping Services) moved their equipment onto the Llama 13-1 location, rigged up, and began pumping in 4000 gals of 20% HCL Acid with approx 650 bbls of sw flush. The acid job was done in four stages. 1000 gals of acid followed by approx 150 bbls of sw. Repeat the process four […]

Llama Update 6.5

As of today we were able to get the flowlines, valves, and fittings hooked up to the tank battery on the Llama 13-2 well. Adam’s well service also put on a coat of paint and has them looking good (see pic below). The only thing we are waiting on is East Central Electric to bring […]

Llama Update 6.3

Today on the Llama 13-2 we spent the better part of the day laying flowlines from the tank battery across the pasture and onto the 13-2 location to the pumpjack, approx. 740′. We were also able to lay the SW line from the SW Pump to the SW Disposal well, approx. 1500′. As of today […]